Table of Contents
PPT Slide
Outline
Hyperion Design OverviewPerformance RequirementsKey System Trades and Critical Analyses
Hyperion Origins
Hyperion Subassemblies
PPT Slide
PPT Slide
PPT Slide
Hyperion Performance Requirements
Key System Trades & Critical Analyses
Hyperion Systems Management Approach
Hyperion Master Schedule
Systems Management Approach
Hyperion Risk Management Process
Hyperion Risk Management Process Overview
Hyperion Risk Items
PPT Slide
PPT Slide
PPT Slide
Hyperion End Item Data Package
Staffing and Resources
Hyperion Technical Review Summary
Technical Review Process
Hyperion Design Reviews
Hyperion Flight Software
Hyperion Ground Software
Hyperion Software Design Reviews & Verification & Validation
Design Review RFA History
Hyperion Product Assurance
Hyperion Product Assurance Documents
Product Assurance Overview
Product Assurance Overview
Hyperion Test and Verification Program Implementation
PPT Slide
PPT Slide
Test Program Implementation
PPT Slide
PPT Slide
PPT Slide
PPT Slide
PPT Slide
PPT Slide
PPT Slide
Hyperion Integration and Test Results
Hyperion Instrument Level Tests at TRW
Tests of Hyperion Following Integration Onto Spacecraft at GSFC
VNIR Spectral Characterization
Hyperion SNR
Hyperion Specification Verification1 of 4
Hyperion Specification Verification2 of 4
Hyperion Specification Verification3 of 4
Hyperion Specification Verification4 of 4
Hyperion Waiver Summary
Hyperion PRs During EO-1 I&T
Hyperion Critical RFAs, PRs and Special Topics1 of 2
Hyperion Critical RFAs, PRs and Special Topics2 of 2
Hyperion Cumulative Operating Time
End-to-End Hyperion Program
Hyperion Readiness
Hyperion Special Topics
PPT Slide
Sensor Exploded View
HSA Baseplate Redesign Summary
Vibration Testing Summary
Baseplate Failure
Base Plate Failure Description
Ultrasound Inspection Utilized
Failure Assessment
Base Plate Modifications
Summary of STM Testing
Summary of HSA Testing
PPT Slide
Cover Description
Cover Sluggish Operation at Cold Temperature
Anomaly Evaluation
Lubrication Characteristics
Improved Cover Operation Reliability
Cover Operation Summary
PPT Slide
PPT Slide
PPT Slide
What Causes the Echo?
Echo Analysis Activities: Summary
Echo Intensity Variation Map
Profiles Before / After Echo Removal
Echo Correction Applied to Hyperion Images
Echo Removal Validation
PPT Slide
VNIR ASP Thermal Noise
Impact of ASP Temperature on VNIR Image
VNIR Noise
VNIR Noise Due to Switching Noise
Impact of ASP Temperature on VNIR Image (2)
Predicted VNIR ASP Temperatures at Beginning of Life for an Orbital Cycle
Predicted VNIR ASP Temperatures at Beginning of Life for an Orbital Cycle
Conclusion
PPT Slide
Causes and Issues
PPT Slide
PPT Slide
PPT Slide
Hyperion Critical RFA (Hyp CDR #5.19)Explain the Hyperion incompatibility with S/C power bus
Hyperion Critical RFA (Hyp CDR 5.21) Explain Hyperion Avg Power of 91W and Allocation of 70W
PPT Slide
Hyperion CDR RFA #5.08:Assure adequate testing of planned lubricant/motor combos
Hyperion CDR RFA #5.14:Recommend sine burst testing for structural verification
Hyperion EIRR RFA #13.01:Address the loose screw in the Hyperion STM
EO-1 PER RFA #9.12: Provide information on the Hyperion structural failure
Hyperion PSR RFA 12.05: Identify temps to which door drive motor has been qualified
PPT Slide
Hyperion CDR RFA #5.23: Effects of temperature changes on gain in the VNIR FPA
Hyperion CDR RFA #5.47: Plan to ensure complete outgassing in initial operation
Hyperion PER RFA #8.12: Understand the ghosting problem
Hyperion PER RFA #8.14: Quantify loss of dynamic range due to ghosting
Hyperion CDR RFA #5.07: Confirm the algorithm for correcting the ghosting
PPT Slide
Hyperion CDR RFA #5.11: Expand & update the verification matrix
Hyperion PSR RFA #13.02:Hold a Failure Review Board for Hyperion
|