Requirements Verification
96 % of the requirements verified
Unverified requirements
- 7 Instrumenter requirements not verifiable before launch because involve providing L&EO support
- Requirement for SVF to perform Level 1 processing of AC data after receipt of code from AC Instrumenters – closed post launch
- 2 CGS requirements to beep FOT and send data via beeper – not launch critical, complete testing by launch
- 24 hour coverage for first 120 days
- SN requirement for SSA service for 2 kbps – opened since transponder had problems
- 4 GN requirements only testable post launch, involves performance of personnel at ground stations