FPPD Lessons Learned Database
Last Update: 1/26/01

---- Sub-Title:  FPPD Database

The following database contains Lessons Learned that have been approved by Code 400.

NO. POC CODE SUBJECT

0001 B. Cramer 491 Skill requirements for technology validation missions.
0002 B. Cramer 491 Budgetary reserve recommendation for technology validation missions.
0003 R. McGlynn 415 Minimizing impacts associated with construction operations at mission critical facilities.
0004 N. Chrissotimos 470 ESSP VCL selection and formulation.
0005 M. Cully 490 EO-1 Solar Array cable wrap damage.
0006 M. Cully 490 HRG exposure to helium.
0007 D. Mengers 410 TWINS International Partnership.
0008 R. McGlynn 415 Approval process for LV/SC ICD changes.
0009 A. Vernacchio 441 HST Servicing Mission Operations training.
0010 R. Fitzgerald 471 Project communications.
0011 R. Fitzgerald 471 Mission Review Team Membership.
0012 D. Lewis 471 Working with foreign contributors to NASA missions.
0013 D. Lewis 471 Working with foreign contributors to NASA missions.
0014 W. Daney 480 NOAA-K AVHRR / HIRS instrument louvers not connected.
0015 D. Tiffany 480 Corporate organizational changes.
0016 D. Crosby 480 AMSU-B EMI / EMC system level testing.
0017 M. Brumfield 480 Core competency of subcontractors.
0018 D. Coolidge 480 NOAA-15(K) S-Band Antenna Failure.
0019 D. Coolidge 480 Satellite deployments.
0024 B. L. Scott 422 Provide detailed WBS for FSW in RFPs.
0025 R. Jenkens 454 Launch services under a fixed price contract.
0026 B. Ochs 426 PI Mode contingency funding.
0037 R. Barthel 454 Requirements flow-down process.
0038 A. Razzaghi 424 Pre-integration testing between instruments and spacecraft.
0040 B. L. Scott 422 Use of software-related GFE in S/C Systems contracts.
0041 B. L. Scott 422 Retain some work in-house on S/C/systems contracted projects.
0042 B. L. Scott 422 Evaluating contractor management thru past experiences.
0045 D. Martin 415 Action Item closure process under a fixed price contract.
0046 D. Martin 415 C&T List Documentation during subsystem CDRs.
0051 D. Helfrich 543 Landsat Solar Array deployment testing.
0052 M. Comberiate 422 Aqua Red Team Review of launch-related issues.